Gombe Gets 480MW Transmission Capacity As FG Upgrades Grid

Published

on

The Federal Government has doubled the upstream electricity transmission capacity of Gombe State to 480 megawatts following the installation of a new transformer at the Gombe Transmission Substation.

The upgrade, alongside the commissioning of a new transmission substation in Billiri, is expected to improve electricity supply and provide additional capacity for more than 70,000 households.

The Minister of Power, Joseph Tegbe, disclosed this on Thursday during the inauguration of the projects, saying they were designed to address growing electricity demand in Gombe and neighbouring communities.

At the Gombe Transmission Substation, Tegbe said an additional 300MVA, 330/132kV transformer had increased the station’s upstream capacity from 300MVA to 600MVA, equivalent to 480MW.

He added that the replacement of an existing 30MVA, 132/33kV transformer with a 100MVA unit had increased the station’s downstream transformation capacity to 220MVA, equivalent to 176MW.

According to him, the upgrades would address suppressed demand caused by the limited capacity of existing infrastructure and accommodate additional electricity consumers.

The minister said the projects reflected President Bola Tinubu’s commitment to strengthening the national grid and improving electricity supply.

At Billiri, the government also inaugurated a new 2x60MVA, 132/33kV transmission substation with a combined capacity of 120MVA, equivalent to approximately 96MW.

Funded by the World Bank and executed by Chris Ejik International Limited, the facility has six outgoing 33kV feeders and is connected to the existing Gombe-Savannah-Yola transmission line.

Tegbe said the substation would improve electricity access for communities and support agricultural activities, businesses and growing settlements in the area.

He urged residents to protect the facilities against vandalism, warning that attacks on electricity infrastructure could disrupt economic activities and household livelihoods.

The Managing Director of the Transmission Company of Nigeria, Sule Ahmed Abdulaziz, said the Billiri substation would strengthen the connection between transmission and distribution networks, ease pressure on existing infrastructure and give Jos Electricity Distribution Company greater flexibility in supplying electricity.

He urged the distribution company to increase its offtake of available electricity to ensure consumers benefit from the investment.

Abdulaziz said the Gombe Transmission Substation reinforcement contract was awarded to ISIN Electromechanical Industries Limited in June 2021 and completed in June 2026.

Representing Governor Muhammadu Yahaya, the state Commissioner for Energy Resources, Sanusi Ahmad, said the projects would support Gombe’s economic expansion.

He said the state was also implementing the Electricity Act 2023 through the Gombe State Electricity Law 2025 and the establishment of the Gombe State Electricity Regulatory Commission.

The Mai Tangle, Danladi Sanusi, commended the investment, saying improved electricity supply could stimulate businesses, attract investors, create jobs and improve healthcare and education.

He, however, urged the authorities to ensure proper maintenance and effective utilisation of the facilities to guarantee lasting benefits.